Outdoor Termination Upgrade at a Cement Works

Shed count raised from two to five per phase against measured dust deposition

Outdoor Termination Upgrade at a Cement Works

Client Background

A cement works was suffering repeated flashovers on the outdoor 11 kV terminations feeding its raw mill and kiln drives. The terminations had been installed with the standard two rain sheds per phase supplied in a generic outdoor kit.

Project Challenge

Stop the flashovers on a site where dust deposition is continuous and a cleaning regime cannot keep up.

Customer Pain Points

  • Continuous dust deposition building a conducting film between cleaning cycles
  • Generic outdoor kits supplied with a shed count sized for a normal site
  • Flashovers stopping production not just tripping a feeder
  • Terminations electrically sound so a rebuild was hard to justify

Our Solution

Shed count was recalculated against the site's actual pollution class and raised from two to five per phase. Additional Y3 sheds were retrofitted over the existing terminations. Where a termination showed surface erosion the outer C101 non tracking layer was replaced before the sheds were fitted.

Manufacturing Process

Sheds molded from the non tracking compound family with factory applied mastic collars. C101 supplied in cut lengths for the terminations that needed a new outer layer.

Supply Chain Coordination

One shipment covering all terminations plus spares. Delivered ahead of the planned kiln shutdown.

Quality Control

Tracking and erosion resistance to ASTM D2303 and colour fastness to IEC 60684-3 verified per lot.

Final Result

Retrofitting was completed during a single kiln shutdown. Flashover events on the upgraded terminations stopped. The site now specifies five sheds per phase as standard for any new outdoor termination.

Customer Benefit

A production stopping fault eliminated by changing one variable that a generic kit had set wrong for the site.

FAQ

Questions About This Project

Why does a generic kit get the shed count wrong
Because a standard kit has to assume a normal pollution class. A cement works a coastal site and a desert site all need more sheds than that assumption allows for.
How is the correct count determined
From the site pollution class and the creepage ratio the applicable standard requires. Tell us the site and voltage class and we will calculate it.
When should the outer layer be replaced rather than covered
If the surface shows tracking or erosion it should be replaced. Sheds fitted over an already eroding surface hide a problem rather than solving it.
Can this be done during a normal shutdown
Yes. Each retrofit takes under twenty minutes once the surface is clean.

Still need an answer ask our engineers on WhatsApp

Discuss a Project Like This One

Tell us the voltage class the quantity and the programme. We will tell you what is realistic before you commit.