Prefab construction contractor in Weifang, Shandong. We engineer…
Quality Prefab House
White and blue accommodation camp serving a hydropower station project in El Salvador
El Salvador · 2016

Hydropower Station Camp El Salvador

Accommodation for a hydropower station project — a tidy white-and-blue camp of dormitories, canteen and offices arranged around landscaped paths.

120+Modules
2Storeys
2016Delivered
Project campUse
Client background

Who the Project Was For

TYAZHMASH supplies equipment for hydropower projects. A hydropower station is built where the water is, which is rarely where the housing is — so the project team needed accommodation on the construction site itself.

Client — TYAZHMASH

Project challenge

What Had to Be Solved

House a project team for the duration of a hydropower construction programme, with the comfort and services of permanent accommodation rather than a temporary camp.

Customer pain points

The Pressures on This Project

A long project duration

People live in a hydropower construction camp for years, not weeks, so the standard matters.

Limited flat ground

Valley sites rarely offer a large level pad.

Services on a construction site

Lighting and sanitary facilities had to be part of the buildings, not a later addition.

A camp that had to look like somewhere to live

Morale on a long project is not a soft issue.

Our solution

What We Supplied and Why

Over 120 detachable units were stacked two storeys high with external steel staircases, which fitted the required accommodation onto the available level ground.

Units were fitted out with finished interiors, lighting and sanitary facilities before shipping, so the camp was serviced accommodation rather than a shell.

Dormitories, canteen and offices were arranged around landscaped paths rather than in a single line, giving the camp the feel of a small settlement.

Manufacturing process

How It Was Built and Shipped

Layout

Building positions and circulation planned around the available level ground.

Fabrication

Frames cut, welded and galvanised; interiors, lighting and sanitary fittings installed and tested.

Packing

Units knocked down flat and loaded to the container plan with photo reports.

Assembly

Units stacked two storeys with external steel staircases and connected to site services.

Supply chain coordination

Getting It There in the Right Order

Shipping to Central America is a long sea leg, so the loading plan was built around maximising units per container and protecting finished interiors in transit.

Quality control

What Was Checked

  • Materials and fittings checked against the approved specification
  • Frame and staircase geometry inspected before galvanising
  • Lighting and sanitary services tested before knock-down
  • Photo report issued before each container was sealed
Final result

What Was Delivered

A white-and-blue camp of dormitories, canteen and offices — over 120 modules stacked two storeys high, fitted out with finished interiors, lighting and sanitary facilities.

Customer benefit

What It Changed

  • Two-storey stacking placed the full accommodation requirement on limited level ground.
  • Finished interiors and services meant the camp was habitable soon after erection.
  • A camp laid out around paths rather than in rows made a multi-year posting more liveable.

Have a Project Like This

Tell us the country, the use and the rough size — we will scope it and quote.