Saudi Arabia — 5,000-Ton Cold-Chain Logistics Cold Storage

Saudi Arabia — 5,000-Ton Cold-Chain Logistics Cold Storage

Feasibility-stage EPC design for a 5,000-ton public cold-chain logistics cold storage at Jeddah Port — a multi-temperature hub for imported frozen food, fresh produce and pharmaceutical cold chain, aligned with Saudi Vision 2030.

  • 5,000 t / 7,200 m²
  • -22℃ to +25℃
  • 10 months
  • 2025
Project Overview

Background And Requirement

As the economic core of the Middle East and its largest agricultural-product importer, Saudi Arabia's demand for low-temperature fresh food, imported produce and pharmaceutical cold-chain products keeps rising. Food imports exceeded US$35 billion in 2023, with cold-chain-dependent fruit, vegetables, meat and seafood making up over 42% — yet the public cold-storage capacity shortfall exceeds 30%, driving up food-circulation losses and retail prices.

This project builds a 5,000-ton public cold-chain logistics cold storage in a core Saudi logistics hub. It fills the regional gap in professional cold storage, serves Red Sea and Persian Gulf port transshipment, supports local food processors and distributors, and meets the growing demand for low-temperature storage of biopharmaceuticals and vaccines.

The site is the logistics park on the north side of Jeddah Port — Saudi Arabia's largest container and bulk-cargo import port, handling over 60% of national fresh-produce imports. It lies just 12 km from the container terminal and 28 km from Jeddah airport cargo, beside the Red Sea coastal highway with quick access to Riyadh and Mecca.

Jeddah's tropical desert climate brings 35–42℃ summer averages and extremes to 50℃. The design thickens insulation, selects high-ambient-rated compressors and oversizes condenser heat rejection to hold refrigeration capacity stable through peak summer, on geologically stable ground free of earthquake and flood risk.

The facility splits into three temperature zones — a 2,800-ton freezer (-18 to -22℃), a 1,600-ton chiller (0 to 5℃) and a 600-ton constant-temperature pharmaceutical room (15–25℃, 45–65% RH) — with ten loading docks, a 4,000 m² yard, and integration with the Saudi customs electronic declaration system for combined storage, clearance and transit.

Project Facts

LocationJeddah, Saudi Arabia
Capacity5,000 t / 7,200 m²
Temperature-22℃ to +25℃
Programme10 months
Completed2025
SectorExport / International

Export and International EPC industry capability

An 18,000 m² site with 7,200 m² of building area split into freezer, chiller and constant-temperature pharmaceutical zones, ten cold-chain docks and a customs-integrated turnover yard — engineered for Jeddah's 50℃ summer extremes.

Scope Of Work

How The Project Was Delivered

  1. 01

    Building & Insulation Design

    Single-storey 9 m steel-structure building on independent reinforced-concrete foundations. 150 mm polyurethane panels (λ ≤ 0.022 W/m·K) cut summer heat ingress by 40%+ versus 100 mm; reflective-coated insulated roof; insulated floor with anti-frost-heave heating; and heated-frame insulated sliding doors.

  2. 02

    Refrigeration System

    Screw-compressor units with high-efficiency condensation rated for 50℃ ambient, with heat-rejection area oversized by 20%. Zoned low-, medium- and constant-temperature compressors with N+1 standby, R404A refrigerant, electric-defrost air coolers, and full PLC control with remote monitoring and unattended operation.

  3. 03

    Electrical & Fire Protection

    Dedicated 10 kV supply with a 1,250 kVA transformer and 500 kW standby generator; high-temperature- and dust-rated equipment for outdoor units; pre-action sprinkler system, automatic fire alarm, zoned fire compartments and emergency lighting to Saudi codes.

  4. 04

    Implementation — 10 Months

    Months 1–2: approvals, land and design review. Months 3–5: civil works and steel structure to topping-out. Months 6–8: insulation, refrigeration and electrical/fire installation and commissioning. Months 9–10: completion acceptance, qualifications and operation.

Equipment And Materials

What Was Supplied

  • Screw-compressor refrigeration units (N+1 standby per zone)
  • High-efficiency evaporative condenser (20% oversized for 50℃)
  • 150 mm polyurethane colour-steel panels (λ ≤ 0.022 W/m·K)
  • Heated-frame insulated sliding cold-store doors
  • Electric-defrost zoned air coolers
  • Environmentally-friendly R404A refrigerant
  • Fully automatic PLC control with remote monitoring
  • 1,250 kVA transformer + 500 kW standby diesel generator
  • Pre-action automatic sprinkler and fire-alarm system
  • Saudi customs electronic-declaration system integration
Saudi Arabia — 5,000-Ton Cold-Chain Logistics Cold Storage — equipment installed on site
Key Outcomes

Results At Handover

US$2.6M

Annual Revenue

At full capacity — storage plus sorting, handling and transit value-added services.

US$1.0M

Net Profit / Year

After electricity, labour, maintenance and taxes at full operation.

US$12.8M

Total Investment

Estimated total project investment across civil, envelope, refrigeration and electrical scope.

Project Data

Temperature Zoning

Functional ZoneStorage CapacityTemperatureRefrigerated AreaShare
Freezer area2,800 t-18℃ to -22℃3,024 m²56%
Cold-storage area1,600 t0℃ to 5℃1,728 m²32%
Pharmaceutical constant-temp600 t15℃ to 25℃648 m²12%
Project Gallery

Photographs From Site

Answers

Questions About This Project

How large is the Saudi Arabia project?

5,000 t / 7,200 m², located in Jeddah, Saudi Arabia.

What temperature does the facility operate at?

-22℃ to +25℃.

How long did the project take?

10 months, completed 2025.

What equipment was supplied?

Key items included screw-compressor refrigeration units (n+1 standby per zone); high-efficiency evaporative condenser (20% oversized for 50℃); 150 mm polyurethane colour-steel panels (λ ≤ 0.022 w/m·k). Full equipment lists are issued with the design pack.

Can Howcool deliver a similar facility for us?

Yes. Send your storage volume or tonnage, target temperature, product type and site location, and our engineers will return a preliminary design and budget estimate within 48 hours.

Planning Something Similar

Send your volume, temperature, product type and location. Our engineers respond within 24 hours with a preliminary design.